|
January 7,
2003
Ed Hughes
Contracting
Officer
Acquisitions
and Grants Group
Centers for
Medicare and Medicaid Services
C2-21-15
7500 Security
Boulevard
Baltimore,
Maryland 21202
Dear Mr. Hughes:
We are writing
on behalf of the Medicare Quality Improvement Organization (QIO) contractors to
detail concerns regarding certain delivery schedule requirements under the Seventh
Scope of Work (SOW7).
Delays in various
products and information from the Centers for Medicare and Medicaid Services (CMS)
and its QIO Support Contractors (QIOSCs) have already caused considerable confusion
as the QIOs plan their work and hire and direct staff. Ultimately, these delays
could lead to compromised contract performance, competitive disadvantages and
escalated costs despite the QIOs’ best efforts to fulfill their contractual
obligations. We believe these delays are likely to adversely influence CMS
evaluations of QIOs, subjecting them to competitive renewal and reduced award
fee.
In addition, certain
of these failures to produce timely deliverables may adversely affect long-term
provider and practitioner perceptions of the dependability and reliability of
QIO contractors, beyond the Seventh Scope of Work. These adverse perceptions may
well compromise the QIOs’ ability to recruit providers and persuade them to invest
the resources needed to achieve measurable improvement in the quality of health
care.
Although the QIO
contract purports to hold the QIOs harmless for performance problems and delays
of certain subcontractors and lead QIOs, it is unclear to what extent CMS intends
to make similar allowances for its own delays. It is also questionable whether
adjustments will be made in the evaluation process to recognize sufficiently the
impact of other parties’ shortcomings on the QIO’s performance.
There may be differences
in the effects of these problems on individual QIOs, and contracting rounds of
QIOs, but all QIOs are at risk of being held responsible for delays and decisions
that were beyond their control. This letter necessarily consists of a list of
problems that require CMS attention. But the point of the letter is not to establish
blame. Rather, we are requesting that you consider each problem area identified
below and work with the AHQA elected leadership and staff to determine how to
avoid unreasonable fee reductions and risk of competitive renewal, despite QIOs
best efforts.
CMS Abstraction
and Reporting Tool (CART)
The continued problems
with the availability and functionality of CART affect the contract performance
of all QIOs. All QIOs are being held responsible for getting at least 50% of the
hospitals in every state to self-report data into the national repository. CMS
is not allowing QIOs to discuss any abstraction tools with hospitals other than
CART, which was due in an operating form to the QIOs on August 1, 2002. This tool
was delivered two and a half months late.
- Beta Version 1.0
was released on August 1, 2002 but was found to be uninstallable.
- Beta Version 1.1
was released on August 9, 2002 but it could not be opened due to lack of instructions
on how to set up a user.
- Installation and
user instructions were released on August 14, 2002.
- Production Version
1.2 was released on October 16, 2002, but had significant functional difficulties.
Some of them have now been addressed but others continue to compromise its usability.
- The Web based
version was supposed to be available in November 2002 but will not be released
until March 2003.
QIOs in states
with a large number of JCAHO-accredited hospitals have to rely on various "Oryx"
vendors [or what are now called Performance Measurement System (PMS) vendors]
in that state to agree to submit data to CMS because hospitals are using vendors
to prepare data for submission. In addition to the delay in delivering CART to
the QIOs, CMS was late in delivering the specifications to the vendors who initially
agreed to incorporate CMS elements into their abstraction tools. In most cases,
this will delay the ability of those vendors to include CART elements in their
proprietary tools until next year.
The only control
QIOs have in this whole situation is "damage control." The delay of
CART and its continued glitches are eroding the QIOs’ progress with hospitals
and their vendors. The delay could force some QIOs to enter several months of
data into CART that was collected by using paper tools, raising costs. Even worse,
it could cause some hospitals and vendors to decide they can no longer trust the
QIOs to deliver on their promise of a functional, reliable abstraction tool. Although
it will be difficult to quantify the effect of these delays on contract performance,
the QIOs cannot be held responsible for a 50% improvement in hospital self-reporting
under these circumstances.
Communications
QIOSC
To date, due to
CMS’ actions and inactions, QIOs have neither the staff nor SOW7 QIOSC support
to do the work required under Task 2a. As of this writing, CMS has not yet issued
an RFP to select a Communications QIOSC. Simultaneously, upon award of the SOW
contracts, CMS provided insufficient funds to continue to support the level of
QIO communications staff employed during the Sixth Scope of Work – when communications
and outreach were less critical to the Administrator’s priorities. QIOs relied
on CMS’ assurances that they could use QIOSC-developed marketing and communication
products during the SOW7 and consequently laid off many of their communications
staff.
Based on an AHQA
survey of QIO Communication Directors, the promise of a Communications QIOSC played
a significant role in QIO's reductions of communications staff. Thirty QIOs responded
to the survey and reported that 24.5 FTEs were lost from the level in the Sixth
Scope of Work. This puts QIOs at an obvious disadvantage as they attempt to perform
successfully under contracts that require a significant new level of outreach
to providers, consumers and the media under several new public reporting efforts.
CMS officials have
told the QIOs repeatedly that they must rely on efficiencies, centralization and
QIO-wide knowledge sharing. The QIOSCs are supposed to be an important element
of this effort. The Communications QIOSC is particularly important to QIOs in
the Seventh Scope due to the thousands of additional providers and millions of
additional consumers the QIOs must reach in order to be successful. This is an
area in which reinventing the wheel could be very costly both monetarily and in
implementing CMS’ highest priority contract subtasks.
Refinements in
the evaluation for Task 2a are unlikely to compensate for the failure to fund
and provide support to CMS’ contractors, but CMS must take into account in the
evaluation its failure to provide a Communications QIOSC. The Task 2a evaluation
is perceived to be highly subjective, and therefore difficult to calibrate. At
the same time, expectations could hardly be higher. The Nursing Home Quality Initiative
was promoted by the Secretary of the Department of Health and Human Services and
the CMS Administrator and made national news. The QIOs must fare well under this
spotlight. It is critical that CMS issue an RFP and contract with a qualified
Communications QIOSC immediately.
PARTner Reporting
System – Monthly Reports and Project Plans
The SOW7 contract
requires QIOs to submit information regarding their ongoing activities using the
PARTner reporting system. The system was expected to be up and running shortly
after the Round 1 QIOs signed their contracts. PARTner was not released, however,
until the end of November and still had some components missing at that time.
The system was not actually useable until mid-December. Furthermore, while the
guide for reporting information into PARTner for Task 1a was finally made available
via SDPS memo on December 31, 2002, similar instructions for other subtasks have
not yet been issued.
This has caused
QIOs to miss several months worth of reports and project plan deadlines, but no
decision has been made regarding what QIOs should do about missed data due to
the delay of PARTner. We strongly recommend that CMS make this decision and then
hold QIOs harmless for a failure to report before PARTner became fully operational.
CMS must properly account for any additional cost associated with retroactive
report submission should it be required. We recommend that QIOs be informed in
writing that they are relieved of any obligation to reformat and submit reports
that could not be filed during the period that PARTner was not fully functional.
PARTner Reporting
System – QIO Work Plan
The PARTner system
was also supposed to accommodate the submission of each QIO’s work plan. Under
the contract, the work plan was due 60 days after each QIO’s contract effective
date, but months after most contracts were signed, PARTner remained unavailable.
In the meantime, QIOs submitted their draft work plans into a temporary Standard
Electronic File Folder (SEFF). Additionally, the QIOs were required under their
contracts to use the CMS template for their work plans, but it was only available
in draft form.
The December 26,
2002 SDPS memo regarding the expected contract modification eliminates the work
plan requirement, but AHQA has learned that at least one Regional Office still
intends to require QIOs in that region to maintain a workplan and produce it for
their inspection during site visits. We support CMS adopting a uniform, national
decision regarding the workplan requirement. However, if ROs are permitted to
insist that contractors maintain a workplan, CMS should state clearly that the
faithful execution of that workplan would be considered during evaluation as evidence
of a QIO’s progress and as proof of changes in their approach to address any problems
they encounter during their work.
Additionally, even
though the workplan requirements are going to be eliminated, we recommend that
CMS notify QIOs that they will be held harmless for their inability to comply
with the contractual requirement to submit the work plan while it was required
and while a workable template and PARTner were unavailable.
GTL/QIOSC Changes
in Deliverables
In the absence
of timely decisions by CMS, Government Task Leaders (GTLs) have been telling QIOs
to act upon expected contract changes. This practice has been troubling
because QIOs are acting upon changes that are not yet reflected during periods
when CMS has provided no official relief from contract deliverable deadlines that
are rapidly approaching. We understand that CMS is working to resolve this problem,
but QIOs are at risk of failing to conform to certain contract requirements while
the process unfolds.
Examples of expected
changes in deliverables include the following:
- Home health
project plan: Some QIOs have heard from the GTL that this deliverable will
be due in five months after the contract start date rather than the contract’s
four-month requirement. The latest proposed contract modification, however, does
not contain this change. In this case, the GTL’s prediction seems not to have
been borne out.
- List of home
health participants: CMS has confirmed the GTL’s prediction in its proposed
contract modification by eliminating the required six-month "lock-in"
period for participants. Some QIOs could still find themselves in apparent non-compliance
with their current contracts at the six-month deadline if the final contract modification
is not issued in a timely manner. Furthermore, if QIOs are going to be expected
to continue their recruitment of home health agencies throughout the SOW7, as
the GTL has stated, CMS must provide sufficient resources for this continued cost.
- Nursing home
chain proposal: While this proposal may yield good results, it has taken CMS
and nursing home chain management several months to reach decisions on the content
of this policy. As a result, the RFP for interested Lead QIOs to implement this
effort was only issued this month. QIOs remain unclear about this proposal’s effect
on their recruitment of identified participants and their overall evaluation if
they have one or more of the participating chains in their state. We request that
CMS provide prompt and official answers to these questions prior to the identified
participant group deadline in February.
- Review Services:
The volume of charts that the GTL and QIOSC expected would have to be reviewed
as part of the effort to ensure inter-rater reliability (IRR) is now confirmed
in the proposed contract modification. However, it also confirms the QIOs’ fear
that the amount of work necessary to this volume of reviews will far exceed contract
resources.
Delay of NHQI
Rollout
The full impact
of the delay of the NHQI rollout on QIO staff resources will not be known until
the QIOs begin to reach their 75% spending mark. To prepare for the high profile
nursing home quality initiative rollout while conserving resources, many QIOs
budgeted their FTEs carefully to transition from one topic to another immediately
following the short-term spike in effort necessary for the rollout. The delay,
which was stretched out from October 23 to November 14, with no clear expectation
of a definite date, caused some QIOs to extend paid time of these personnel.
While these circumstances
are beyond their control under the contract, QIOs are accountable for downgraded
performance and reduced fee as a result of delays in executing work under other
subtasks due to staff remaining engaged in a task that was scheduled for completion.
Some allowance must be made for the ripple effect of CMS’ delay on the performance
of other work.
In closing, AHQA
acknowledges that CMS is attempting many unprecedented initiatives, and is encountering
unexpected difficulties in the course of doing so. We do not expect CMS to be
flawless in executing its obligations under the contract. We do ask that CMS recognize
that its performance and timeliness has and will have a profound impact on the
performance of QIO contractors, particularly where the contract specifies reliance
on CMS deliverables that are not available on schedule. We ask CMS to acknowledge
that it would be inappropriate for delays or failures in these government deliverables
to force competitive renewals and reduced payment of award fees under the contract
that would not have occurred if CMS’ deliverables had been timely and fully functional
and to adjust its evaluation accordingly.
Our recommendations
are offered in the spirit of a cooperative effort between the federal government
and its contractors, both of which are jointly engaged in an ambitious and worthwhile
effort to improve the quality of health care for older and disabled Americans.
Thank you for your
attention to these matters. AHQA leaders and staff look forward to meeting with
you in Baltimore on January 10, 2003 to further discuss these problems and their
solutions.
Sincerely,

David G. Schulke
Executive Vice President
cc: Stephen
Jencks, M.D.
|